At the final stage of construction of a logistics centre (commissioning works), during the spring‑summer soil thawing period, part of the column foundations (21 units) underwent uneven settlement. Geological surveys carried out during the construction stage did not reveal waterlogged or marshy soils under part of the building. The surveys were carried out in winter on frozen ground, which caused inaccurate determination of the physical and mechanical characteristics of the soils.
Task:
Strengthen the foundation soils, stop uneven settlement of the column foundations. Confirmation of the work result is the lifting of the foundations by 1–3 mm.