Settlement of the base slabs at a railway depot in Farnham, near London, threatened to disrupt railway operations in south‑eastern England. The 60‑year‑old slabs had been gradually settling for many years due to embankment consolidation, drainage problems and erosion, as well as increased loads from modern rolling stock. The problem reached a critical point when 6,000 square metres of service area, vital for operations, were at risk of closure due to unsafe foundation conditions. URETEK was chosen as the contractor to solve the problem without disrupting scheduled train traffic.
Goals
Stabilise the foundation beneath the slabs and level the railway track by lifting the settled sections.