During the work, settlement of the ballast layer was detected. The tunnel laying was suspended until the ballast layer was restored and safety at the work site was ensured. According to the geological survey report, the base was made of homogeneous stone material, most likely irregular stones 5–20 cm in size, without fine aggregate. This structure is characterised by a significant void content. According to data from similar work on the Zagreb–Rijeka line, the approximate porosity coefficient is 35% in the upper part and 30% in the lower part. The most likely cause of the settlement was the collapse of the pipeline channel due to vibrations associated with the excavation. After the protective pipe was removed, it was decided to cement the section affected by the settlement. The attempt failed because the voids between the stones were too large to hold the concrete. Meanwhile, the settlement of the embankment continued (about 5 cm per week), and to compensate for the deformations, the ballast layer was repeatedly topped up with new stones at short intervals.
Goals
Thanks to a precise analysis, the most affected areas at the tunnel excavation site were identified, where injection using URETEK® technology was planned. The main goal was to stabilise the current situation and prevent future deformations.