URETEK considers this project successful, as this is the opinion of the customer himself. Both parties find the following factors positive:
- The project was carried out during a scheduled railway shutdown determined by the customer.
- The competence and speed of the URETEK team, as well as the unique properties of the material, allowed the customer to repair four times more track than originally planned for the same budget.
- Other repair work required on this section of the railway track was successfully combined with URETEK’s work, and the customer did not have to take additional operational breaks.
- Water flows were successfully redirected and the railway track was stabilised.
- The customer intends to include URETEK’s work in next year’s budget and entrust the company with stabilising even more railway tracks.