Project: Production building
Location: Saint Petersburg, Russia
Year: 2015
Duration: 5 days
Technology: DEEP INJECTION & SLAB LIFTING
Eliminating the consequences of the Vimm-Bill-Dann Company's drawdown
Problem
Instability of floor slabs and local subsidence
Solution
Stabilization of the foundation soil and leveling of the floor slab
Problem
OJSC Wimm‑Bill‑Dann, one of the largest dairy producers in Russia. In September 2015, using URETEK technology, work was carried out to stabilise the foundation soils of the reinforced concrete floor slab, as well as to fill voids in unused utilities.
Solution
The work was completed within 5 calendar days without stopping production, and all signs of the work were also eliminated. After the work was completed, the company provided an extended warranty to OJSC Wimm‑Bill‑Dann.
Standard projects and pricing
If the project description does not satisfy you, request a project consultation with a geotechnical engineer to get your own assessment of Uretek technologies
Leave your phone number and our consultant will contact you