Project: A three-storey residential building with a basement
Location: Rostov region
Year: 2019
Duration: 2 working days
Technology: DEEP INJECTION
Restoration work after soaking and weakening of the foundation of a three-storey residential building
Problem
Uneven settlement of a building after a pipe burst
Solution
Restoration of the bearing capacity of the base
Problem
A water pipe burst caused wetting of the foundation base soils and, as a result, uneven settlement of the building. Numerous cracks appeared. During the survey, weakened soil layers in need of strengthening were identified.

Task:
Strengthening the soils in the foundation base of the building.
Solution
Work was carried out to strengthen the foundation base soils of the strip foundation to a depth from -1.2 meters to -2.8 meters. Strengthening of the foundation base soils using URETEK technology was performed by injecting an expanding geopolymer composition URETEK into the weakened soil layer.