After repeated tests, it was established that the Uretek project had been successfully implemented. The service life of the existing road slabs was significantly extended, avoiding the need to reconstruct the entire section of concrete road with large‑scale traffic closures, despite the continuing deterioration of the structures. In just 77 working days, 48,568 square metres of road slabs were stabilised. Due to cost savings, the customer decided to also use Uretek to stabilise the concrete road slabs on the nearby Inanda Road after completion of the initial contract and to continue in the eastbound direction on the Solomon Mahlangu Highway in the near future.